Monthly Archives: September 2016

Road paving nearly completed

In September, 2016 the remaining section of Middle Fork road was paved, from Valley Camp to Champion Beach. A short section at the problematic cliffs near Champion Beach will be finished in 2017 under a new contract. It’s not a smooth drive all the way to the Taylor River bridge.

Paving completed in 2016

Paving completed in 2016

More miles paved in August

In the last 2 weeks of August, 3.5 more miles of the Middle Fork road were paved, from Champion Beach to Big Blowout Creek. Weather permitting, project management expects to pave the rest of the road to Valley Camp before the end of construction for this year on October 31, 2016.

2016augpaving

3.5 miles paved in August, 2016


20160831NewPaving01

New pavement in progress with asphalt trucks coming out

20160831NewPaving02

Second layer of asphalt being applied

20160831NewPaving03

A worker cleans years of accumulated cruft from the concrete bridge rails

20160903NewPaving04

Cleaned concrete bridge

20160903NewPaving05

New pavement by rock outcrop before Wise Creek

20160903NewPaving06

Newly paved approach to Bessemer Gate

20160903NewPaving07

Paved wiggle in road just after the Bessemer Gate

20160903NewPaving08

Newly paved pullout at upper Oxbow Loop

20160903NewPaving09

Newly paved pullout at Russian Butte view

20160903NewPaving10

Newly paved pullout at Pratt River Bar